Greenfield
Projects
Bed Linen Project - Hassan
|
- Integrated
manufacturing facility with a capacity of 60,000 metres per day
- Acquired 120
acres of land at Hassan SEZ.
- Project to be
implemented in two phases.
Phase-1 at a cost of Rs 2710 millions is scheduled for completion by
October,2006.
Phase-2 capex of Rs 1290 millions likely to be completed by Q1 2007.
|
|
Current Status – Bed
Linen Project, Hassan |
- Construction
started on 7th October 2005 - Total built up area of 60,000 sq meters.
- Building work to
finish by September 2006
- Concluded orders
for Weaving, Process and Preparatory machines
- Concluded order
for highly automated biological effluent treatment plant with water
recovery system
- Vendors are all
top European manufacturers like Benninger, Monforts, Osthoff, Kuesters.
- Trial Production
to start by November 2006
|
|
Made-ups Project –
Apparel Park |
- Integrated
manufacturing facility with a capacity of 4,000 pieces per day
- Acquired 8.53
acres of land at apparel park, Doddaballapur.
- Project to be
implemented in two phases. Phase-1 will be at a cost of Rs 240 millions
is scheduled for completion by September,2006.
- This unit will
focus on Luxury brands & domestic markets. The annual revenue by the end
of year 2009-10 is projected to be around Rs 1000 millions
|
|
Current Status -
Made-ups Project, Apparel Park |
- Construction
started on February, 2006- Total built up area of 12,253 sq meters
- Building work to
finish by September 2006.
- Concluded orders
for 2 Embroidery machines.
- Vendors are all
top European & Japan manufacturers like ZSK, Durkopp, Juki, Electrolux…
- Trial Production
to start by August 2006.
|
| |
|
| |